Public Asset Creation
Development Works & Infrastructure Projects Monitor
Transparent physical and financial tracking of community halls, rural roads, water supply, and solar projects across East Siang.
ESP-PRJ-2026-01FY: 2025-2026
In ProgressConstruction of Multi-Purpose Gram Panchayat Community Hall & Digital CSC
Location: Balek Village, Balek Gram Panchayat•Scheme: 15th Finance Commission Tied Grant•Agency: Panchayat Engineering Cell / Balek GP Committee
Physical Progress Milestone75% Completed
Sanction Amount₹24,50,000
Expenditure Incurred₹18,00,000
Commencement Date10 Aug 2025
Target Completion30 Sept 2026
Field Inspection Report:
RCC roof casting completed. Interior electrical fitting and citizen service kiosk wiring under execution.
Stage Progression:
Foundation & Earthwork15%
2025-08-15Site clearance and plinth level masonry completed.
Superstructure & Brickwork50%
2025-12-20Wall brickwork and beam reinforcement completed.
Roof Casting & Plastering75%
2026-06-10Slab curing done. Plastering underway.
ESP-PRJ-2026-02FY: 2025-2026
COMPLETEDSolar Powered Mini-Grid and Deep Borewell Drinking Water Filtration System
Location: Kiyit, Kiyit Gram Panchayat•Scheme: Jal Jeevan Mission & 15th FC Co-funding•Agency: PHED & Kiyit VWSC
Physical Progress Milestone100% Completed
Sanction Amount₹18,00,000
Expenditure Incurred₹18,00,000
Commencement Date01 Oct 2025
Target Completion15 Apr 2026
Field Inspection Report:
Fully operational. Supplying 55 LPCD potable water to 180 households with 10kW solar backup.
Stage Progression:
Borewell Drilling30%
2025-10-15120m deep tube well successful with high discharge.
Commissioning & Water Quality Testing100%
2026-04-10Safe drinking water parameters verified by district laboratory.
ESP-PRJ-2026-03FY: 2025-2026
In ProgressInter-Village Cement Concrete Road & Storm Water Drainage (Length 1.2 KM)
Location: Romang to Mebo Charali, Mebo Gram Panchayat•Scheme: Arunachal Gram Swaraj Abhiyan•Agency: Rural Works Department (RWD)
Physical Progress Milestone65% Completed
Sanction Amount₹32,00,000
Expenditure Incurred₹22,00,000
Commencement Date05 Nov 2025
Target Completion15 Oct 2026
Field Inspection Report:
Sub-base and 800m CC pavement laid. Side drainage construction in progress.
Stage Progression:
Subgrade Preparation20%
2025-11-20Grading and compaction of rural alignment.
Concrete Pavement65%
2026-05-15M25 concrete paving completed for first section.